Eskom aims to end load reduction by March 2027
Eskom says its grid has stabilised, with spare capacity and far lower diesel spending, and it wants to end load reduction in affected areas by March 2027.
Eskom says its power system has improved markedly, and the utility has set March 2027 as its target for ending load reduction in the areas still affected, according to SAnews.
The utility says it has not implemented load shedding for over 550 days in a row, a run that began in May last year. Its year-to-date Energy Availability Factor has risen by about 12.57% to 68.13%. Average unplanned outages are down by 7 090MW.
Spare capacity and lower diesel costs
Eskom says it currently has roughly 4 274MW of generating capacity beyond what customers need. It says this could support energy-intensive industries, new investment and industrial growth, and could allow more electricity to be exported to the region.
The utility also says it is burning far less diesel in its open-cycle gas turbines. Diesel spending so far this financial year is R1.284 billion, compared with R6.080 billion over the same period last year, a saving of R4.796 billion.
On the environment, Eskom reported that relative particulate emissions were still within its target at the end of October 2026, as they have been since October 2025.
El Niño and the weather
Eskom does not expect El Niño to threaten electricity supply or grid stability. It acknowledged that hotter weather could cause some coal-fired units to lose output, increase the curtailment of daytime renewable energy and raise export demand because of drought in neighbouring countries that rely on hydropower.
The utility says it could absorb about 2 000MW of heat-related losses and still keep a cushion of around 5 000MW in peak periods.
Where load reduction still applies
Eskom says illegal connections and meter tampering still damage equipment and create safety risks in some localised areas. It keeps load reduction in place there as a temporary, targeted protective measure.
To end it by March 2027, Eskom has begun a phased programme covering 971 feeders in all provinces. The programme should benefit about 1.69 million customers out of a total base of 7.2 million. The planned steps include:
- rolling out smart meters;
- integrating Distributed Energy Resources;
- expanding Free Basic Electricity support;
- running customer education programmes.
Eskom says seven of the nine provinces are now free of load reduction. About 1.6 million customers who were affected are back on normal supply, leaving 102 551 customers still affected.
What this means for you
Load reduction is separate from load shedding, and it applies only in certain high-risk areas. If you live in one of them, the planned smart meters and customer education drive are the changes to watch for. Eskom says its focus is now on sustaining these gains and turning better generation performance into capacity that supports economic growth.
This story is based on reporting by SAnews.